Upgrading at Potgietersrus 132/33 kV substation
The project made provision for the complete refurbishment, re-design & upgrading / expansion of the Potgietersrus 132/33 kV substation. Design, tender process and project management phase were included, all as per Eskom Distribution processes (ERA, TEF, DRA, FRA, etc,) This included all installation, erection, primary & secondary plant, earth works, transformers, buildings, and power & control cables, etc, commissioning and handing-over in a proper working condition of the substation to Eskom.